Łódź checks 100 tenement houses on the tunnel route. The worst fears are confirmed
The diameter tunnel in Łódź encounters serious problems. The contractor said that the fears arising from previous research of tenement houses on the construction route were confirmed.
In September 2024, a fragment of the tenement sighed on the route of the Łódź cross -city tunnel. After that event, a crisis staff was established, which, together with the investor, was to examine the buildings over the dig.
Construction of a railway tunnel near Łódź. The buildings will not stand it?
A spokesman Przedsiębiorstwo Budowy Road and Mostów from Minsk Mazowiecki has just announced the effects of control. – They confirmed the results from previous research that many buildings on the tunnel route are in a bad or emergency state – said Piotr Grabowski.
Let us point out that it is about buildings between al. 1 Maja and Przystanek Łódź Śródmieście. Now PBDIM is checking the tenements from the Łódź Śródmieście stop to Łódź Fabryczna.
– We have already transferred the results of results from the first stage of the inventory of buildings to the investor – PKP PLK. We also indicate the proposed technologies for protecting buildings, as well as the real cost of this task. Decisions, what to do with tenements, belong to the investor – added the spokesman.
Łódź. Examination of a wide belt over the future tunnel
Grabowski reminded that the main tunnel designer wanted to broaden the examined area over the tunnel. Now buildings are checked on the land belt width from 70 to even 100 meters along the tunnel being built. Some neighboring buildings are also checked, because in Łódź many tenement houses have common structural elements, even walls.
The spokesman added that the contractor had already indicated the objects suitable for demolition, and only some of them were demolished. This was the effect of social protests that took place at the turn of 2021 and 2022. It was then decided to leave the maximum number of objects above the tunnel route.
When is the tunnel under Łódź? Talks are underway
Piotr Grabowski explained that even the order of buildings is being checked. In the case of the September disaster, it was a key aspect. The rights of the pitched tenement house had only one its own wall. The others belonged to neighboring buildings.
– It is possible that expert opinions will help make difficult decisions about possible demolition of tenements, which are in the worst technical condition – said the spokesman. Initially, the construction of the tunnel was to be completed in June 2026. After interrupting the tunnel drilling in September 2024, the contractor submitted an application to postpone this deadline for a year. Negotiations are ongoing.